The time required to complete an activity under abnormal or extremely adverse condition in which everything goes wrong, with the exception of delays due to acts which cannot be foreseen is called

1
Optimistic time
2
Most likely time
3
Pessimistic time
4
Probabilistic time
5
None of the above