engineering recuitment FCI JE 2022 Mock Test for CE/ME/EE (Phase I & II) Construction Materials and Management Project Planning PERT
The float that can be used by an activity without affecting successor activities is
1
Total Float
2
Free Float
3
Independent Float
4
Interfering Float
5
None of these