engineering recuitment FCI JE 2022 Mock Test for CE/ME/EE (Phase I & II) Construction Materials and Management Project Planning
In construction industry, the conformance cost associated with preparing work instructions and checklist, drafting specifications, training of staff and workmen is classified as
1
Prevention cost
2
Appraisal cost
3
Failure cost
4
Inventory cost
5
Internal failure cost