engineering recuitment FCI JE 2022 Mock Test for CE/ME/EE (Phase I & II) Construction Materials and Management Project Planning CPM
Resource smoothing means
1
Optimization and economical utilization of resources
2
gradual increase in resources
3
adjustment of resources to have the least variations
4
complete revamping of resources to suit the requirements
5
None of these