Which of the following test is carried out to ensure the sufficient strength of insulation between two or more conductors to avoid leakage between them?
1
Testing of insulation resistance between wiring and earth
2
Testing of insulation resistance between conductors
3
Testing of polarity of single phase switch
4
Testing of earth continuity path