engineering recuitment WBMSC Sub Assistant Engineer Civil Mock Test 2023 Estimating, Cost and Valuation Valuation
The sanction of the detailed estimate, design calculations, quantities of works, rates and cost of the work by the competent authority of the Engineering department is known as:
1
Expenditure sanction
2
Administrative approval
3
Technical sanction
4
None of the above