P and Q working together completed a work in 10 days. If P worked twice as efficiently as he actually did and Q worked 2/3 as efficiently as he actually did, then the work would have been completed in 6 days. How many days P alone will take to complete the work?

1
11(2/3)
2
14
3
13(1/3)
4
12