Match List – I and List – II, and select the correct answer using the codes in given below list.
|
List-I |
List-II |
||
|
i. |
Preliminary estimate |
1. |
Probable variation for quantity rate and amount for each items |
|
ii. |
Revised estimate |
2. |
Material deviation of a structural nature |
|
iii. |
Supplementary estimate |
3. |
Complete estimate |
|
iv. |
Quantity estimate |
4. |
Approximate cost of the project |
1
i – 4, ii – 1, iii – 2, iv - 3
2
i – 4, ii – 2, iii – 1, iv - 3
3
i – 3, ii – 1, iii – 2, iv - 4
4
i – 3, ii – 2, iii – 1, iv - 4