If the optimistic time, most likely time and pessimistic time or activity A are 4, 6 and 8 weeks. Respectively and for activity B are 5, 5.5 and 9 weeks respectively, then

1
Expected time of activity A is greater than the expected time of activity B
2
Expected time of activity B is greater than the expected time of activity A
3
Expected time of both activities A and B are same
4
Data too inadequate to compute expected times of activities