engineering recuitment TNPSC AE Civil 2024 Test series Construction Materials and Management Project Planning PERT
Which one of the following is the amount of time by which the start of an activity may be delayed without delaying the start of a following activity?
1
Total float
2
Interference float
3
Independent float
4
Free float