Which one of the following is NOT the characteristic of equipment management and scheduling?

1
Work should be planned and scheduled to achieve the fullest use of every equipment item, minimizing idle equipment time.
2
To the maximum extent possible, equipment sent to the job should be of the type that will best perform the work under actual job conditions.
3
The temptation to overload equipment in an effort to get more production is common but counterproductive.
4
Examination of weight and dimension limit of the road for carrying heavy equipment.