engineering recuitment TNPSC AE Civil 2024 Test series Construction Materials and Management Project Planning PERT
What is the formula to calculate the 'expected time' (a = optimistic time, m = most likely time, b = pessimistic time)
1
Te = (2a + 4 m + b)/6
2
Te = (a + 4 m + b)/6
3
Te = (a + 4 m + b)/8
4
Te = (a + 4 m + 5b)/6