A small construction project consists of the jobs as given in the table below.

Job

Normal 

duration (days)

Minimum 

duration (days)

Cost of crashing

(INR per day)

1-2

9

6

20

1-3

8

5

25

1-4

15

10

30

2-4

5

3

10

3-4

10

6

15

4-5

2

1

40

Consider the overhead total costs of INR. 60 per day

If the optimum length of schedule is 15 days, then the total cost of the project will be ________INR.

Enter numerical value using the virtual keypad. Round off where necessary.

Sponsored