engineering recuitment GATE CE 2023-24 Test Series Environmental Engineering Disposing of Sewage Effluents
A city with a population of 100000 and a average sewage flow of 120 lpcd is locatedon a stream with rate of flow of 0.7 m3/sec. The BOD of sewage is 210 mg/lt. The DO of and BOD content of stream above the outfall sewer are 7.8 and 1 mg/lt respectively. Then the total BOD of the stream immediately upon discharging the sewage into the stream in kg / day is _______
Enter numerical value using the virtual keypad. Round off where necessary.