Consider the following activity for the total project:

Activity

Immediate Predecessors

Duration (Days

A

-

10

B

-

9

C

A

9

D

A

8

E

B

7

F

B

11

G

D, E

5

The total project duration for the critical path will be

1
25 days
2
23 days
3
21 days
4
19 days