engineering recuitment GATE CE 2023-24 Test Series Construction Materials and Management Project Planning PERT
For the given network details. Calculate the total float for an activity 4 - 7 of the networks.
|
Activity |
Estimated duration |
Activity |
Estimated duration |
|
A |
5 |
F |
2 |
|
B |
2 |
G |
3 |
|
C |
6 |
H |
8 |
|
D |
4 |
I |
7 |
|
E |
4 |
J |
2 |
1
0
2
1
3
2
4
4