Find out the critical path and duration of following project network:

Activity Duration Predecessor
A 2 NIL
B 4 A
C 3 A
D 6 B, C
E 7 B
F 3 D, E

1
Critical path = ABEF, Duration = 15 Days
2
Critical path = ABEF, Duration = 16 Days
3
Critical path = ABDF, Duration = 16 Days
4
Critical path = ABDF, Duration = 15 Days