engineering recuitment GATE CE 2023-24 Test Series Industrial Engineering Operations Research PERT and CPM
A project is expected to take 60 weeks with a variance of 20.25. Within how many weeks would the project be expected to be completed with the probability of 90%?
|
Z |
- 1.67 |
1 |
1.28 |
2 |
|
P(z)% |
5 |
84 |
90 |
97 |
Enter numerical value using the virtual keypad. Round off where necessary.