A two activity network data is given by the table. The project overhead costs are Rs. 400 per day. The least cost plan for the network is

Activity

Normal duration

Normal cost

Crashing duration

Crash cost

1 - 2

6

7000

4

9000

2 - 3

10

9000

5

13000

1
22,400 /-
2
23,400 /-
3
36,000 /-
4
24,000 /-