For the following detail of the network, which of the following activity should be crashed first?
|
Activity |
Normal duration (weeks) |
Normal cost (Rs.) |
Crash duration (weeks) |
Crash cost (Rs.) |
|
1 - 2 |
4 |
4000 |
2 |
12000 |
|
2 - 3 |
5 |
3000 |
2 |
7500 |
|
2 - 4 |
7 |
3600 |
5 |
6000 |
|
3 - 4 |
4 |
5000 |
2 |
10000 |
1
1 - 2
2
2 - 3
3
2 - 4
4
3 - 4