The given table lists the project's activities, precedence relationships and duration. Find the critical path of the project.

Activity Precedence Duration (in days)
P - 3
Q - 4
R P 5
S Q 5
T R, S 7
U R, S 5
V T 2
W U 10

1
P-R-U-V
2
P-R-T-U
3
Q-S-T-U
4
Q-S-U-W