Consider the following network diagram in which the activity durations are given along side each arrow. The critical path for the project will be ________

1
1 – 3 – 4 – 6 – 7
2
1 – 2 – 4 – 5 – 7 
3
1 – 3 – 5 – 6 – 7
4
1 – 2 – 4 – 6 – 7