engineering recuitment BHEL Engineer Trainee Mock Test 2025 Construction Materials and Management Project Planning CPM
Consider the following network diagram in which the activity durations are given along side each arrow. The critical path for the project will be ________
1
1 – 3 – 4 – 6 – 7
2
1 – 2 – 4 – 5 – 7
3
1 – 3 – 5 – 6 – 7
4
1 – 2 – 4 – 6 – 7