engineering recuitment UKPSC Polytechnic Lecturer Mock Test 2024 Industrial Engineering Production Planning and Inventory Control Inventory Control
When ordering cost is increased to 64 times then, EOQ will be increased to:
1
2 times
2
4 times
3
8 times
4
Remains same