engineering recuitment UKPSC Polytechnic Lecturer Mock Test 2024 Construction Materials and Management Project Planning PERT
Total float can be expressed as:
(a) latest start time - earliest start time
(b) latest finish time - earliest finish time
1
Both (a) and (b) are false
2
(a) is true but (b) is false
3
Both (a) and (b) are true
4
(a) is false but (b) is true