engineering recuitment UKPSC Polytechnic Lecturer Mock Test 2024 Industrial Engineering Operations Research PERT and CPM
Negative slack occurs when -
1
Events stick to their schedule
2
Dummy activities are large in number
3
Activities lie in critical path
4
There is deficiency of resources