engineering recuitment UKPSC Polytechnic Lecturer Mock Test 2024 Construction Materials and Management Project Planning PERT
Consider the following statement in accordance with PERT and CPM. Which of the following is not correct?
1
Both PERT and CPM network consist of activities and events.
2
PERT is based on deterministic approach and CPM is based on probabilistic approach.
3
PERT follows B-distribution while CPM follows normal distribution.
4
PERT is in event-oriented network and CPM is an activity-oriented network.