Consider the network with at time indicated on arrows. Time & costs are given in table below.

Activity

Time (weeks)

Cost

Normal

Crash

Normal

Crash

1 – 2

8

6

1200

2000

1 – 3

14

12

1300

2800

2 – 4

12

4

1500

3900

3 – 6

10

8

1000

1900

4 – 5

4

2

900

1400

4 – 6

10

8

1100

2300

5 – 7

8

6

1800

2100

6 - 7

14

12

400

600

What will be increase in cost if project is crashed by 4 days to complete it earlier? 

Enter numerical value using the virtual keypad. Round off where necessary.