The workmen in an engineering company are expected to work for 400 minutes in a shift of 8 hours. The remaining time is meant for rest and personal need etc. What is the standard time per piece of a job whose normal time is 2 minutes?
1
2.40 minutes
2
4.80 minutes
3
1.08 minutes
4
1.5 minutes