For a project, the detailed activities with duration and cost is shown in the table.

It is also given that indirect cost is Rs. 900 per day

Activity

Normal

Crash

\(\frac{{\Delta C}}{{\Delta T}}\)

Time (day)

Cost (Rs)

Time (day)

Cost (Rs)

1-2

3

500

2

1000

500

1-3

2

750

1

1500

750

1-4

6

1400

4

2600

600

2-4

5

1000

3

1800

400

2-5

7

1150

6

1450

300

3-4

2

800

2

800

0

4-5

4

1000

2

2400

700

1
The optimum time to complete the project after crashing = 10 days
2
Total cost of the project = Rs. 16400
3
The optimum time to complete the project after crashing = 9 days
4
Total cost of the project = Rs. 16500

Sponsored

hivanix.in

Visit

This quiz is brought to you by hivanix.in

🌐 Web App Development

Quick Navigation