engineering recuitment GATE ME 2023-24 Test Series Industrial Engineering Production Planning and Inventory Control Aggregate Production Planning and Scheduling
A set of jobs are to be processed on a single machine using shortest processing time rule. Find the average tardiness per Job (in minutes).
|
Jobs |
A |
B |
C |
D |
E |
F |
G |
H |
|
Processing Time |
14 |
10 |
7 |
17 |
13 |
9 |
16 |
8 |
|
Due date |
51 |
79 |
62 |
71 |
84 |
81 |
59 |
95 |
1
4.7
2
5.2
3
6.9
4
6.3