The correct sequence of operation in production planning and control is:
1
Routing → Scheduling → Dispatching → follow up
2
Scheduling → Dispatching → Follow up → Routing
3
Dispatching → Routing → Scheduling → Follow up
4
Routing → follow up → Dispatching → Scheduling