Consider a simplex problem:

Maximum : Z = 5x1 + 10x2 + 8x3

S.T : 3x1 + 5x2 + 2x3 < 60 …….. Material

4x1 + 4x2 + 4x3 < 70 …….. M/C hours

2x1 + 4x2 + 5x3 < 100 …….. Labours

Basic

x1

x2

x3

S1

S2

S3

RHS

Z

11/3

0

0

2/3

5/3

0

160

x2

1/3

1

0

1/3

- 1/6

0

8

x3

2/3

0

1

-1/3

5/12

0

10

S3

-8/3

0

0

1/3

- 17/12

1

18

If the machine hours decreased by 12 hours then the new production at ‘B’ is:

[where : x1, xi & x3 are the no. of units of A, B & C produced respectively. Sii S2 & S3 are the slack variables]

1
8
2
10
3
6
4
5