A PERT project network consists of 5 activities A to E. The time estimates of these activities follow Beta-distribution. The predecessor—successor (P-S) relationships between the nodes and time estimates of activities are given in table.

Activity

P – S

Optimistic time

(days)

Most likely time

(days)

Pessimistic time

(days)

A

1 – 2

2

4

6

B

2 – 3

4

5

12

C

2 – 4

5

8

11

D

3 – 5

2

5

08

E

4 – 5

4

6

14


The variance (in day2) of the critical path is ______ (round off to 2 decimal places)