engineering recuitment GATE ME 2023-24 Test Series Industrial Engineering Operations Research PERT and CPM
The normal duration and normal cost of activity are 24 days and Rs. 50,000 respectively. The activity crash duration is 22 days and the indirect cost is Rs1000 per day. If the cost slope is Rs. 1500 per day, then the total cost of activity after the crashing will be:
1
Rs. 47,500
2
Rs. 54,500
3
Rs. 51,000
4
Rs. 45,500