engineering recuitment GATE ME 2023-24 Test Series Industrial Engineering Production Planning and Inventory Control Aggregate Production Planning and Scheduling
The time required for two operations cutting and binding for 5 jobs are as follows:
|
Job No. |
1 |
2 |
3 |
4 |
5 |
|
Cutting (min) |
8 |
6 |
2 |
5 |
7 |
|
Binding (min) |
8 |
7 |
7 |
6 |
4 |
What is the optimal makespan sequence?
1
2-4-1-3-5
2
3-4-2-1-5
3
1-2-3-4-5
4
3-5-2-4-1