engineering recuitment GATE ME 2023-24 Test Series Industrial Engineering Operations Research PERT and CPM
In any crash program for a project
1
Both direct and indirect costs increase
2
Indirect costs increase, and direct costs decrease
3
Direct costs increase, and indirect costs decrease
4
cost are of no criterion