Amit can do 3/4th of work in 15 days. Efficiency of Bhavesh is 25% more than that of Amit. Both Amit and Bhavesh started working together and left the work after five days. Chandan completed the remaining work in 14 days. Efficiency of Chandan is what percent more/less than that of Amit ?

1
20%
2
12.5%
3
25%
4
37.5%