Consider five processes, P0,P1,P2,P3,P4  and three resources A,B,C.Given below are the maximum needs and currently allocated resources to these processes.

 

Max needs

Currently Allocated

 

A

B

C

A

B

C

P0

7

5

3

0

1

0

P1

3

2

2

2

0

0

P2

9

0

2

3

0

2

P3

2

2

2

2

1

1

P4

4

3

3

0

0

2


Total resources->A-10; B 5; C 7

What is the safe sequence? 

1
P2 P3 P2 P4 P0
2
P0 P1P3P4P2
3
P1P0P2P4P3
4
P3P1P4P0P2