engineering recuitment NMC JE Civil Mock Test 2024 Construction Materials and Management Project Planning PERT
In PERT analysis, the probability of completion of the project in 40 days will be (given : earliest expected time, TE of last event is 40 days)
1
0%
2
100%
3
Less than 100%
4
50%