Which of the following is a wrong statement?

1
PERT is suitable for projects having probabilistic time estimates
2
CPM is suitable for projects having deterministic activities
3
Both PERT and CPM are event oriented
4
PERT is event oriented, while CPM is activity oriented
5
PERT is a three-time estimate technique