engineering recuitment OPSC Assistant Industries Officer Mock Test 2025 Quantitative Aptitude Time and Work
12 Students working for 8 hours in a days complete the project in 25 days.In how many days can 16 students working for 10 hours a day complete the same project ?
1
15 Days
2
18 Days
3
21 Days
4
10 Days