engineering recuitment PGCIL Diploma Trainee Mock Test 2024 Estimating, Cost and Valuation Measurement
According to Which Indian Standard Code, the Brickwork rate for arches of span not exceeding 6 m hire and labour charges for centering and shuttering shall be included in the item and for spans exceeding 6 m centering and shuttering shall be measured separately?
1
IS: 1200
2
IS: 1220
3
IS: 1400
4
IS: 1240