engineering recuitment BSPHCL Technician (Electrician) 2024 Mock Test Power Systems Economies of Power Generation Load Factor
A generating station has maximum demand of 25 MW and average load on generating station is 15 MW. What will be the load factor?
1
0.2
2
1.66
3
0.6
4
0.8