engineering recuitment UPSSSC JE Civil 2024 Mock Test Irrigation Engineering Water Requirement of Crops
The delta for a crop having base period 130 days is 65 cm. What is the duty?
1
< 1715 hectare/cumec
2
(1715 < duty < 1728) hectare/cumec
3
> 1730 hectare/cumec
4
= 1728 hectare/cumec