engineering recuitment UPPSC AE Mock Test 2024 Industrial Engineering Operations Research PERT and CPM
Statement 1: The critical path in PERT represents the shortest path in a project network.
Statement 2: Activities on the critical path have zero slack time.
1
Statement 1 is true, and Statement 2 is true.
2
Statement 1 is true, but Statement 2 is false.
3
Statement 1 is false, but Statement 2 is true.
4
Statement 1 is false, and Statement 2 is false.