engineering recuitment UPPSC AE Mock Test 2024 Construction Materials and Management Project Planning CPM
7, 10 and 15 months are the optimistic, the most likely duration and the pessimistic time estimates in respectively in a network. What will be expected time?
1
7 months
2
10 months
3
10.33 months
4
10.67 months