engineering recuitment DRDO Technician A 2022 Mock Test Series (Tier I) Quantitative Aptitude Time and Work Work Efficiency
A person completes \(\frac{3}{5}\)th of certain work in 21 days. Then how many days it will take to finish the remaining work.
1
7 days
2
14 days
3
13 days
4
35 days