engineering recuitment DRDO Technician A 2022 Mock Test Series (Tier I) Quantitative Aptitude Time and Work Work Efficiency
A can do a piece of work in 12 days. B is 50% more efficient than A. In how many days B will finish the same work?
1
8 days
2
12 days
3
24 days
4
6 days