A can do a work in 12 days and B in 16 days. They undertook to do it for Rs. 6000 with the help of ā€˜C’ they completed the work in 6 days. What is the share of A?

1
Rs. 2880
2
Rs. 3000
3
Rs. 1440
4
Rs. 2400