engineering recuitment BPSC AE Mock Test 2025 Construction Materials and Management Project Planning CPM
Which of the following conclusions is/are correct in relation to the given network diagram?
(i) Activity B is controlled by activity A.
(ii) Activity D is controlled by both activities A and C.
(iii) Activity B is independent of activity C.
1
Only (i) and (iii) are correct.
2
Only (i) is correct.
3
Only (i) and (ii) are correct.
4
All the conclusions are correct.